Saturday, June 16, 2007

more completions

Upstairs washroom with second coat of paint (lower half of walls) and accessories reinstalled (completed).






The threshold between the living room and kitchen has been stained and urethaned (completed).


Bedroom #3 on the East wing has the furniture returned (completed).


Friday, June 15, 2007

washrooms, take 2

The door to the 1st floor washroom from the living room is completed.




The 1st coat of 967 has been applied to the tile panels in the 2nd floor washroom.

Thursday, June 14, 2007

washrooms

Upstair washroom. The tile panels have been primed.





Main floor washroom. The door has been installed and has 1st coat of paint.

Wednesday, June 13, 2007

bedroom #3 and upstairs washroom

Bedroom #3 completed. Baseboards and quarter rounds installed.




The upstairs washroom. Upper half of walls painted. The glass of light fixture replaced.





Monday, June 11, 2007

Sanding and priming

The patching, sanding and priming of the upstairs washroom (upper half of walls) has been completed.





The washroom door primed.


The trim primed of the west wing.

The baseboard and quarter round primed at top of stairway.

finishing touches

The red door entrance to living room completed. Excellent. With brass kickplate, handle and lock. (Applied 2 coats of white primer, then 2 coats of grey primer and then needed 2 coats of red enamel where rolled, plus 3 coats of red enamel where brushed.)



The pine plank threshold between the living room and washroom completed with 3 coats of urethane.

Sunday, June 10, 2007

sneak peek

The living room entrance door freshly painted. One more coat of paint to go and removing the painter's tape.



The threshold between the living room and the kitchen sanded. Ready for a coat of urethane.

bedroom #3 on the east wing

All trim and doors painted, plus installed new light fixture.



The hardwood strip floor has been painted to match the other bedroom floors.



The walls have been painted.